Projects

  • Building Demolition
  • Building Refurbishment
  • Decommissioning, Dismantling & Packing of Plant
  • Schedule Waste Mitigation & Disposal
  • Steel Structure Dismantling

Demolition Klang Bus Stand, Plaza Warisan & Pasaraya UO for MRT Pasar Seni Underground Station, Jalan H.S. Lee. Kuala Lumpur

LOCATION : Kuala Lumpur
SYNERGY ROLE : Building Demolition
TIMELINE : 12 months

DESCRIPTION : Building demolition for future MRT station

Demolition of front façade and Carpark for AEON Shopping Center, Jln Jejaka, Tmn Maluri, Cheras, K.Lumpur

LOCATION : Kuala Lumpur
SYNERGY ROLE : Building Demolition
TIMELINE : 4 months

DESCRIPTION : Ramp demolition with live building

Jakel Mall Refurbishment

LOCATION : Kuala Lumpur
SYNERGY ROLE : Commercial Building Refurbishment
TIMELINE : 12 months

DESCRIPTION : Mall refurbishment work

Membaikpulih dan Menaiktaraf Bangunan Sultan Abdul Samad

LOCATION : Kuala Lumpur
SYNERGY ROLE : Heritage and building conservation
TIMELINE : 12 months

DESCRIPTION : Internal refurbishment works and roof repair work

BDO PLANT DEMOLITION AND SALVAGE PROJECT

LOCATION : BASF Petronas Chemicals Sdn Bhd Plant, Gebeng, Kuantan
SYNERGY ROLE : Decommissioning, Dismantling, Demolition, Salvaging Of BDO Red Cracker Plant As Scrap
TIMELINE : 2022 – 10 Months

DESCRIPTION : Dismantling, Demolition & Disposal Of BDO Red Cracker Plant. Make Good Pipe Bridge Structure / Remain As Live Plant Supply

Disassembly, Packaging, Labelling And Land Transport Of 2 x 110MW Frame 9E Gas Turbines And Balance Of Plant At Pasir Gudang Power Station GF2

LOCATION : TNB Pasir Gudang Power Station, Johor Darul Ta’zim
SYNERGY ROLE : Dismantling, Tagging, Packing, Synchronisation And Logistics To Local Port For Export
TIMELINE : 6 Months

DESCRIPTION : 2 x Gas Turbine Dismantling, Packing And Shipping To Client For Reassembly And Commissioning

Disassembly, Packaging, Labelling And Land Transport Of 2 x 110MW Frame 9E Gas Turbines And Balance Of Plant At Putrajaya Power Station

LOCATION : TNB Putrajaya Power Station, Putrajaya, Wilayah Persekutuan Putrajaya
SYNERGY ROLE : Dismantling, Tagging, Packing, Synchronisation And Logistics To Local Port For Export
TIMELINE : 6 Months

DESCRIPTION : 2 x Gas Turbine – Dismantling, Packing And Shipping To Client For Reassembly And Commissioning

Dismantling, Disassembling, Packing, Labelling, Tagging and Transporting of 4 X 109MW Open Cycle Gas Turbine Plant (OCGT) and Balance Of Plant (BOP) At The Port Dickson Power Plant

LOCATION : PDP – Malakoff, Port Dickson Power Plant, Negeri Sembilan Khusus
SYNERGY ROLE : Dismantling, Tagging, Packing, Synchronisation And Logistics To Local Port For Export
TIMELINE : 12 Months + 8 Months(MCO)

DESCRIPTION : 4 x Gas Turbine Dismantling, Packing And Shipping To Client For Reassembly And Commissioning

Decommission, Dismantle & Demolish 2 x 120 MW Conventional Steam Plant (CSP) Units, Stesen Janaelektrik Sultan Iskandar (SJSI), Pasir Gudang

LOCATION : Johor Malaysia
SYNERGY ROLE : Decommissioning, Dismantling & Demolition of 2x 120 MW CSP
TIMELINE : 12 months

DESCRIPTION : Disposal of power transformers, Disposal of all scheduled waste, Dismantling steel structure

Decommission, Dismantling & Demolition of GF2, 4 X 130MW Open Cycle Gas Turbine (OCGT) at Stesen Jalanelektrik Jambatan Connaught, Klang, Selangor

LOCATION : Klang, Selangor, Malaysia
SYNERGY ROLE : Decommission, Dismantling & Demolition of power plant
TIMELINE : 12 months (contract) – Completed in 10 months

DESCRIPTION : Disposal of power transformers, dismantling of Gas Turbine Scheduled Waste management and disposal, steel structure dismantling.

Demolition of Colgate Palmolive Powder & Liquid Plant, Decontamination, Scheduled Waste Handling and Disposal, Petaling Jaya. Selangor

LOCATION : Subang Jaya
SYNERGY ROLE : Decommissioning, Dismantling & Demolition of production factory
TIMELINE : 5 months

DESCRIPTION : Factory dismantling and demolition, disposal of schedule waste

Cadangan Membina Laluan Pejalan Kaki Berbayar Yang Menghubungkan Terowong Bawah Tanah Dari Stesen MRT Muzium Negara Ke Bangunan Stesen KL Sentral Demolition, Diamond Cutting, Link Bridge Demolition & Dismantling

LOCATION : Kuala Lumpur
SYNERGY ROLE : Bridge Dismantling
TIMELINE : 8 months

DESCRIPTION : Bridge Dismantling & Demolition Above Jalan Stesen Sentral 5

Decommission, Dismantle & Demolish 2 x 120 MW Conventional Steam Plant (CSP) Units, Stesen Janaelektrik Sultan Iskandar (SJSI), Pasir Gudang

LOCATION : Johor Malaysia
SYNERGY ROLE : Decommissioning, Dismantling & Demolition of 2x 120 MW CSP
TIMELINE : 12 months

DESCRIPTION : Disposal of power transformers, Disposal of all scheduled waste, Dismantling of steel structure, Demolition of chimney

Decommission, Dismantling & Demolition of GF2, 4 X 130MW Open Cycle Gas Turbine (OCGT) at Stesen Jalanelektrik Jambatan Connaught, Klang, Selangor

LOCATION : Klang, Selangor, Malaysia
SYNERGY ROLE : Decommission, Dismantling & Demolition of power plant
TIMELINE : 12 months (contract) – Completed in 10 months

DESCRIPTION : Disposal of power transformers, dismantling of Gas Turbine Scheduled Waste management and disposal, steel structure dismantling.

Demolition of Cabot (M) Malaysia Sdn Bhd

LOCATION : Port Dickson
SYNERGY ROLE : Decommissioning, Dismantling & Demolition, Schedule Waste Management
TIMELINE : 9 months

DESCRIPTION : Factory dismantling and demolition, disposal of schedule waste

Demolition of Granulation Plant at CCM Fertilizer Sdn. Bhd.

LOCATION : Shah Alam, Selangor
SYNERGY ROLE : Steel structure dismantling & Schedule Waste Management
TIMELINE : 8 months

DESCRIPTION : Factory dismantling and demolition